faq’s

Timeline to Opening

Wondering what’s going on and what the plan is? It took us a minute to get the ball rolling - far longer than we ever anticipated, but we’ve finally made some major progress and construction is underway.

Here’s an extremely rough estimate of construction plans…

AUGUST 2024

✅ Entrance road

✅ Water well

✅ Excavation for underground to begin

✅ UTV Invasion August 28-31st

* Waiting on Eastern Idaho Health Department to approve Septic

SEPTEMBER 2024

✅ Power & Water excavation begins

✅ Roads and Sites Surveyed and Staked

OCTOBER 2024

✅ Building Delivered

✅ Well Pump Installed

NOVEMBER 2024

* Heavy Excavation Continues

DECEMBER 2024

* Excavation Continues (there’s a crap-ton of lava rock)

✅ Rocky Mountain Power brings Power to Sand Box Entrance

January 2025

✅ Stilllllllllll excavating

✅ Still waiting on approval of Septic from Eastern Idaho Health Department (approval required for building permit).

FEBRUARY 2025

Cutting in Sites / Grading

Rock Removal / Excavation

MAY 2025

Water Conduit being pulled throughout park

Grading Sites

JUNE 2025

Power Conduit being pulled through park

Power Pedestals and Water Hydrants installed at sites

AUGUST 2025

Septic Permit Approved

SEPTEMBER 2025

Building Erected

Grading Sites

OCTOBER 2025

Septic System Installed

Site Reservations opened!

Sand Box hit the road for UTV Takeover in Sand Hollow, St. George, UT.

Grading Sites

NOVEMBER 2025

✅ Building Interior: Plumbing | Electrical | Floor

Freezing our tails off but making friends with the coyotes, mice, maggots and deer.

Grading Sites

Landscaping: Fire Pits

DECEMBER 2025

Continue Building Interior Plumbing

Build out building interior | Public Bathrooms & Store areas

Complete Grading Sites

Continue Landscaping: Fire Pits

JANUARY 2026

Continue Building Interior: Bathroom Buildout and Store Area | Electrical

FEBRUARY 2026

✅ Continue Building Interior Buildout: Finish Framing | Electrical | Finish Plumbing

MARCH 2026

* Complete Building Interior: Electrical | Drywall | Paint | Finish work | Cabinetry

* Landscaping: Sprinklers | Plant Sod | Plant Trees | Grading Sites | Roads | Road Base | Gravel Pads

APRIL 2026

* Grand Opening

While the above outline is our current plans - we don’t yet know what we don’t know. So flexibility is the name of the game. Things could change. We hope not, but ya know…..life.

So - here it is as we know for now…