Wondering what’s going on and what the plan is? It took us a minute to get the ball rolling - far longer than we ever anticipated, but we’ve finally made some major progress and construction is underway.

Here’s an extremely rough estimate of construction plans…

AUGUST 2024

✅ Entrance road

✅ Water well

✅ Excavation for underground to begin

✅ UTV Invasion August 28-31st

* Waiting on Eastern Idaho Health Department to approve Septic

SEPTEMBER 2024

✅ Power & Water excavation begins

✅ Roads and Sites Surveyed and Staked

OCTOBER 2024

✅ Building Delivered

✅ Well Pump Installed

NOVEMBER 2024

* Heavy Excavation Continues

DECEMBER 2024

* Excavation Continues (there’s a crap-ton of lava rock)

✅ Rocky Mountain Power brings Power to Sand Box Entrance

January 2025

* Stilllllllllll excavating

* Still waiting on approval of Septic from Eastern Idaho Health Department (septic approval is required for

building permit to erect building).

FEBRUARY 2025

* Building Erection

* Cutting in Sites / Grading

While the above outline is our current plans - we don’t yet know what we don’t know. So flexibility is the name of the game. Things could change. We hope not, but ya know…..life.

So - here it is as we know for now…